Rotating shift schedules are used when an operation needs 24/7 coverage and the workforce cannot be permanently assigned to fixed shifts. The right schedule depends on crew availability, the nature of the work, fatigue considerations, and labor cost constraints. There is no universally best pattern.
The most common mistake is choosing a schedule based on what sounds good on paper without modeling it against actual crew availability and workload. A DuPont schedule requires four crews; if you only have enough workers for two crews, it is not an option. A 12-hour schedule gives workers more days off, but if your operation involves heavy machinery or safety-critical decisions, the fatigue tradeoff may not be acceptable.
This guide walks through the major patterns, explains the crew count and fatigue implications, and provides a framework for evaluating transition costs and long-term sustainability.
The Patterns and What Makes Them Different
The DuPont schedule is a 28-day cycle with four crews working 12-hour shifts. The pattern is 4 days on, 4 days off, 3 nights on, 3 off, 4 days on, 4 off, 4 nights on, 4 off. Each crew averages 42 hours per week. The long blocks of days off are attractive to workers, but the rapid day-to-night transitions can be fatiguing.
The Pitman (2-2-3) schedule is a 14-day cycle with two crews working 12-hour shifts. The pattern alternates: 2 on, 2 off, 3 on, 2 off, 2 on, 3 off. Common in smaller operations where staffing four crews is not feasible. Workers alternate between day and night every two weeks, which is hard on circadian rhythms.
The 4-on-4-off schedule is an 8-day cycle with four crews working 12-hour shifts. Four consecutive days or nights, then four days off. Simple, predictable, easy to remember. Less common than DuPont but used in industries where simplicity outweighs the need for longer breaks.
The Continental schedule is a 21-day cycle with four crews working 8-hour shifts, rotating through day, swing, and night. More frequent schedule changes and shorter shifts. Some workers prefer it. The complexity of tracking three shift times can be confusing. Still averages 42 hours per week despite shorter shifts.
Crew Count Drives Everything
The number of available workers determines which schedules are even possible. You cannot run a DuPont with two crews. You cannot run a Pitman with four. Count your workers and determine how many crews you can field before evaluating patterns.
For 24/7 coverage with two crews, your option is Pitman (2-2-3) or similar. Each crew works half the days, alternating day and night. Works if you have 8 to 12 operators.
For four crews, you have DuPont, 4-on-4-off, and Continental as options. Need 16 to 24 workers depending on shift length and absenteeism. The advantage is longer breaks and less frequent day-to-night transitions. The disadvantage is higher total headcount.
If you are between crew sizes (12-14 workers, tight for four crews, plenty for two), you need to decide whether to hire up or accept a two-crew pattern. The tradeoff depends on your labor market, budget, and the consequences of fatigue or turnover.
Fatigue and the 12-Hour Question
12-hour shifts are popular because workers get more days off. But fatigue increases exponentially after hour 10. Error rates climb, reaction times slow, and injury risk goes up. Night shifts are worse than day shifts. This is not a comfort issue; it is a performance and safety issue.
Research consistently shows that cognitive performance degrades significantly after 10 hours of continuous work, and the effect is worse at night. A worker on hour 11 of a night shift is functionally impaired to a degree comparable to mild alcohol intoxication.
Industries with high injury rates or safety-critical operations often limit shifts to 8 or 10 hours. The Continental schedule (8-hour) reduces per-shift fatigue. The tradeoff is more frequent handoffs, which introduce their own risks if communication is poor.
Rotating from day to night is harder than fixed shifts. The circadian rhythm takes several days to adjust, and most rotating schedules do not allow enough time. Workers report more sleep problems, higher stress, and worse health outcomes. If you have the option to run fixed day and night crews instead of rotating everyone, that is the least fatiguing choice.
Transitioning From Fixed to Rotating
Switching from fixed to rotating shifts is disruptive. Workers who have been on permanent day or night shifts will resist. The key is transparency, advance notice (at least 30-60 days), and clear communication about why the change is necessary.
Run both schedules on paper for 2-4 weeks before the transition. Show every worker their exact shifts for the first month. This eliminates confusion and gives time to adjust family schedules and childcare.
Seniority battles over crew assignment are the number one friction point. In a four-crew system, one crew always starts on the most favorable rotation. The fairest approach is to rotate crew assignments periodically so nobody is permanently stuck with the worst rotation.
Use the anchor date feature in scheduling tools to align the new pattern with pay periods and planned shutdowns. Small alignment details make the schedule easier to manage and reduce administrative friction.
Shift Schedule Generator
Generate DuPont, Pitman, 4-on-4-off, and Continental shift calendars with built-in pay and overtime calculator. See your gross earnings per pay period, customize crew colors, and download printable PDF schedules.
What the Schedule Costs You
DuPont, Pitman, and Continental all average 42 hours per week, which means 2 hours of overtime per week in jurisdictions with a 40-hour threshold. Over a year, that is 104 hours of overtime per worker. For 20 workers at $25/hour base and 1.5x overtime, that is $78,000/year. That may be acceptable, or it may blow your budget.
Some states have daily overtime thresholds (California: anything over 8 hours). In those jurisdictions, 12-hour schedules trigger 4 hours of overtime per shift, making the schedule significantly more expensive. Verify your overtime rules before committing.
Schedule complexity also has an administrative cost. A Continental schedule with three shift times requires more oversight and coordination than a simple 4-on-4-off. Miscommunications and confusion increase with complexity.
Model the actual cost before you commit. Input your overtime rules, base rates, and shift differentials. Run the schedule for a full cycle. The difference between patterns may be thousands of dollars per week.
DuPont: 42 hrs/week
Pitman (2-2-3): 42 hrs/week
4-on-4-off: 42 hrs/week
Continental: 42 hrs/week
4x10: 40 hrs/week
9/80: 40 hrs/week
Patterns averaging 42 hrs/week trigger 2 hrs/week overtime in most jurisdictions.