Skip to main content
Productivity 8 min read Feb 25, 2026

Managing Weather Delays in Construction

Tracking methods, make-up strategies, cost impacts, and contract provisions for weather-impacted projects

Weather is the most common cause of schedule delay in construction and the most frequently disputed. Every outdoor project will lose days to rain, snow, extreme heat, high winds, or frozen ground—the question is how many days, whether those days entitle the contractor to a time extension, whether they also entitle the contractor to additional compensation, and how make-up work is scheduled to recover lost time. The answers depend on the contract language, the baseline weather assumptions, and the quality of your daily tracking.

Effective weather delay management starts before the first shovel hits the ground: establishing baseline expectations in the contract, setting up daily weather tracking systems, and building float into the schedule for expected weather events. This guide covers the legal framework, practical tracking methods, recovery strategies, and the cost impacts that weather delays impose beyond just lost calendar days.

Excusable vs. Compensable Delays

Contract law classifies delays into three categories. Excusable, non-compensable delays entitle the contractor to a time extension (more days to finish) but not additional money. Most weather delays fall here—the contractor gets extra calendar days but absorbs the cost of idle labor, equipment, and extended overhead. Excusable, compensable delays entitle the contractor to both time and money, but weather-related compensable delays are rare and typically require proving the weather was "unusually severe" beyond what was reasonably foreseeable. Non-excusable delays are the contractor's fault and receive neither time nor money.

The key distinction for weather is "foreseeable vs. unforeseeable." A contract for exterior work in Chicago from November to March should anticipate some freezing days—those are foreseeable and typically non-compensable (the contractor should have built them into the bid schedule). A freak ice storm in June, however, may qualify as an excusable and potentially compensable delay because it was not reasonably foreseeable. The baseline for "foreseeable" is usually the 10-year or 30-year weather average for the project location and season.

Federal contracts (FAR 52.249-10, Default clause) explicitly allow time extensions for "unusually severe weather." The contracting officer compares actual weather events to historical averages (often using the National Weather Service 30-year normal data) and grants additional days only for weather that exceeds the baseline. For example, if the historical average shows 5 rainy days in April for the project county and the actual count is 9, the contractor may receive a 4-day time extension. Only the excess over the anticipated baseline qualifies.

FAR weather clause: Under federal contracts, the contractor must submit a written request for time extension within 10 days of the weather event. The request must compare actual weather to the anticipated baseline and demonstrate that the weather actually prevented work on critical-path activities. Late notice can result in denial regardless of merit.
Productivity

Rain Day & Weather Delay Tracker

Track weather delay days against contract allowance, project schedule impact, and compare delay costs versus Saturday make-up work with regional precipitation benchmarks.

Launch Calculator →

Weather Day Tracking Methods

Accurate daily weather tracking is essential for supporting time extension claims. At minimum, maintain a daily log that records: temperature (high/low), precipitation (type and amount), wind speed, ground conditions (frozen, muddy, dry), and the impact on each trade or activity. "Rained all day" is not sufficient documentation. "0.75 inches of rain between 6 AM and 2 PM; site access roads impassable; concrete pour postponed; iron crew stood down at 10 AM due to wet steel and lightning within 5 miles" is.

The best tracking method combines your daily superintendent report with data from a nearby NWS weather station. Weather station data provides objective, third-party verification of conditions that is difficult to dispute in a claim. Identify the nearest ASOS (Automated Surface Observing System) station to your site—most airports have one—and record the station ID in your project files. You can pull historical daily data from the NWS Climate Data Online archive at any time, but contemporaneous daily logging from the job site is stronger evidence because it documents the actual impact on work.

Define "weather day" criteria in your project-specific quality/safety plan: a full weather day (no productive work possible), a partial weather day (some activities impacted but others proceed), and a non-impact day (weather present but work continues normally). A light drizzle may stop exterior painting but not interior electrical rough-in. Only days where weather prevents critical-path work should count toward time extension requests. Document which specific activities were impacted and why, not just that it rained.

Tip: Photo documentation: Take timestamped photos of site conditions on weather-impact days. A photo of a flooded excavation, a muddy access road, or ice-covered structural steel is worth more than any written description in supporting a time extension claim.

Make-Up Scheduling Strategies

Saturday work: The most common recovery method. Adding a 6th workday at straight time (if the CBA allows) or at overtime rates recovers 8–10 hours per week. On a 50-day delay exposure, working 5 Saturdays can recover 2–3 calendar weeks. The cost is overtime premium (if applicable), supervision for the extra day, and fatigue-related productivity loss if sustained more than 3–4 weeks. Most union agreements allow Saturday work at 1.5× rates; some allow it at straight time with advance notice.

Extended shifts: Moving from 8-hour to 10-hour days adds 10 hours/week (2 hours × 5 days). This is often more cost-effective than Saturday work because the incremental cost is only the overtime premium on 2 hours/day versus 8 hours on Saturday, and crew mobilization happens only once per day instead of an extra time on Saturday. However, sustained 10-hour days for more than 4 weeks produce measurable productivity loss (see the six productivity factors). Use 10-hour shifts for short-term recovery (2–4 weeks) and revert to normal schedules once the float is recovered.

Crew stacking: Adding additional crews or increasing crew sizes to accelerate production. This works when the work can be physically subdivided (e.g., different floors, different systems, different areas of a site) but backfires when crews are stacked into the same work area, causing congestion losses that offset the additional labor. Crew stacking is most effective on projects with linear or repetitive work (pipeline, roadway, multi-building sites) and least effective on single-space projects (one building, one room). Estimate the congestion factor before committing to a stacking strategy.

Warning: Diminishing returns: Working 6 × 10-hour days for more than 4 weeks produces less net output than 5 × 10-hour days because fatigue-induced productivity loss on the 6th day and overtime hours erases the extra hours. Short, intense recovery pushes (2–3 weeks) are far more effective than sustained schedule compression.
Productivity

Overtime Cost Projection Tool

Analyze the true cost of overtime including hidden costs like turnover, fatigue incidents, FICA, and workers comp. Compares OT strategy vs hiring additional staff with break-even analysis.

Launch Calculator →

Cost Impact of Weather Delays

The direct cost of a weather delay day includes standby labor (workers report to the site, cannot work, may receive show-up pay per the CBA—typically 2–4 hours), idle equipment rental (you pay the daily/monthly rate whether the crane operates or not), and extended general conditions (superintendent, project manager, trailer, utilities, insurance—prorated at $2,000–$10,000 per day depending on project size). These are real, measurable costs that add up quickly.

Indirect costs are harder to quantify but often larger: subcontractor delay claims (downstream trades waiting for you to finish), liquidated damages if the project misses its completion milestone, lost revenue for the owner if the facility cannot open on time (which becomes the contractor's problem if the delay is deemed non-excusable), and opportunity cost of tying up your workforce and equipment on a stalled project instead of starting the next one. On a $20 million commercial project, extended general conditions alone run $5,000–$8,000 per calendar day, and 20 weather delay days produce $100,000–$160,000 in overhead cost before any recovery efforts.

Build weather contingency into bid pricing, not just the schedule. If the 30-year average shows 15 weather-impact days for your project's location and duration, price those 15 days of extended general conditions into the bid. The schedule should show the impact as float or as explicitly calendared non-work days. Trying to absorb weather costs from profit margin is a recipe for losses on any project longer than 3 months.

Formula: Weather day cost estimate: (Show-up pay × crew size) + (Equipment daily rate × idle equipment count) + (Daily general conditions rate) = Direct cost per weather day. For a 30-person crew with 3 major equipment pieces: ($120 show-up × 30) + ($1,500 × 3) + $5,000 = $13,100 per weather day.
Productivity

Per Diem & Travel Pay Calculator

Calculate per diem, lodging, mileage, and mobilization costs with GSA rate tiers, first/last day 75% rule, meal deductions, and IRS mileage rates. Includes rate lookup guidance.

Launch Calculator →

Contract Provisions and Documentation

The time to negotiate weather delay provisions is during contract formation, not after delays occur. Key contract provisions to review and negotiate: the definition of a "weather day" (full day lost vs. partial impact), the baseline for "anticipated" weather (30-year NWS average vs. 10-year vs. project-specific), the notice requirement for claiming weather delays (typically 5–10 days), whether the contractor gets time only or time and money, and the method for calculating additional compensation if compensable.

On private contracts, weather provisions vary widely. Some contracts give the contractor automatic time extensions for any day with measurable precipitation. Others require proof that weather prevented critical-path work. The most onerous contracts treat all weather as the contractor's risk with no time extensions. If you are bidding a 12-month outdoor project with zero weather days in the contract schedule, either add weather contingency to your price or negotiate a weather clause—do not assume the owner will be reasonable after the fact.

Force majeure clauses may cover extreme weather events (hurricanes, tornadoes, record-breaking cold) that exceed anything in the historical record. Standard force majeure language typically requires the event to be beyond the parties' control, not reasonably foreseeable, and impossible (not just difficult or expensive) to work through. A Category 4 hurricane qualifies. A heavy rainstorm in spring probably does not. Review force majeure language carefully and understand the notice requirements, which are often strict (written notice within 48–72 hours of the event).

Tip: Pre-bid weather analysis: Before bidding outdoor work, pull 30-year weather data from NOAA for the project county and months of planned work. Calculate the expected number of weather-impact days and price them into your bid. This takes 30 minutes and can prevent a 6-figure loss.

Frequently Asked Questions

Use the 30-year average for the project location and season. NOAA's Climate Data Online provides monthly precipitation days, temperature extremes, and wind data by county. A typical rule of thumb for the eastern US is 3–5 weather-impact days per month for outdoor work, but this varies dramatically by region and season.
Usually no. Most weather delays are excusable but non-compensable—you get a time extension but no additional money. Compensable weather delays typically require proving the weather was "unusually severe" beyond what was reasonably foreseeable for the project location and season. Contract language governs the specifics.
Maintain daily logs recording temperature, precipitation, wind, ground conditions, and the specific impact on each trade. Supplement with data from the nearest NWS weather station (ASOS). Take timestamped photos. Identify which critical-path activities were prevented. Submit formal notice within the contract's required timeframe (typically 5–10 days).
Direct costs include show-up pay (2–4 hours per worker), idle equipment rental, and daily general conditions. For a typical commercial project, this runs $5,000–$15,000 per weather day depending on crew size and equipment. Indirect costs (cascading trade delays, extended overhead, potential LDs) can multiply this significantly.
Yes, if the weather was reasonably foreseeable (within historical norms for the location and season), if you did not provide timely written notice, or if the weather did not actually prevent critical-path work. Strong documentation, prompt notice, and comparison to the historical baseline are your best defenses against denial.

Calculators Referenced in This Guide

Productivity Live

Overtime Pay Calculator

Calculate overtime pay with federal FLSA and state-specific daily OT rules for California, Alaska, Colorado, and Nevada. Handles anti-pyramiding, prevailing wage fringe, and common schedule presets.

Productivity Live

Job Labor Estimator

Estimate construction man-hours by trade and task with productivity adjustments for weather, overtime, site conditions, night shift, confined space, and elevated work.

Productivity Live

Rain Day & Weather Delay Tracker

Track weather delay days against contract allowance, project schedule impact, and compare delay costs versus Saturday make-up work with regional precipitation benchmarks.