Skip to main content
Electrical 10 min read Feb 14, 2026

Transformer Sizing Using NEC Article 220 Demand Factors

General lighting loads, appliance demand, range and dryer calculations, single-phase vs three-phase sizing, and selecting standard kVA ratings

Transformer sizing determines how much power is available to a building or facility. Undersizing causes voltage drop, overheating, and nuisance tripping. Oversizing wastes money on equipment and increases no-load losses that run 24/7. The goal is to size the transformer to carry the calculated demand load with a reasonable margin for future growth.

NEC Article 220 provides demand factors that reduce the connected load to a realistic demand load. Without demand factors, a 200-unit apartment building with 200 ranges would need a transformer sized for 200 × 12 kW = 2,400 kW. With Table 220.55 demand factors, the range demand drops to roughly 65 kW — a 97% reduction that reflects the reality that all ranges never operate at full power simultaneously.

This guide covers the NEC Article 220 calculation method, demand factors for each load category, single-phase versus three-phase considerations, and how to select the right standard kVA transformer size.

General Lighting Load and Table 220.12

NEC Table 220.12 assigns a unit load in volt-amperes per square foot based on building occupancy type. Dwelling units: 3 VA/ft². Office buildings: 3.5 VA/ft². Retail stores: 2.25 VA/ft². Warehouses: 0.25 VA/ft². Industrial commercial: 2 VA/ft². Schools: 3 VA/ft². These values cover general lighting and general-use receptacles.

Calculate the total general lighting load by multiplying the building area by the unit load value. For a 2,000 ft² dwelling: 2,000 × 3 = 6,000 VA. This load is then subject to the demand factors in Table 220.42.

Table 220.42 demand factors for dwelling units: first 3,000 VA at 100%, remainder from 3,001 to 120,000 VA at 35%. For the 6,000 VA example: 3,000 × 1.0 + 3,000 × 0.35 = 3,000 + 1,050 = 4,050 VA demand.

For non-dwelling occupancies, the demand factors differ. Hospital and hotel lighting uses the same tiers as dwellings. Warehouses get 100% for first 12,500 VA, 50% for the rest. All others get 100% of the total lighting load with no reduction.

Formula: Dwelling general lighting demand:
Total VA = Floor area (ft²) × 3 VA/ft²
Demand: First 3,000 VA at 100% + remainder at 35%

Example (2,400 ft² home):
Total = 2,400 × 3 = 7,200 VA
Demand = 3,000 + (4,200 × 0.35) = 3,000 + 1,470 = 4,470 VA
Electrical

Electrical Service & Transformer Sizing Calculator

Size transformers using NEC Article 220 demand factors. Enter your load inventory to calculate demand kVA and select the standard transformer size for single-phase or three-phase service.

Launch Calculator →

Appliance, Range, and Dryer Demand Factors

Fixed appliances in dwelling units (dishwasher, disposal, water heater, etc.) get a demand factor under NEC 220.53. If there are four or more fastened-in-place appliances other than ranges, dryers, A/C, and space heating, the total nameplate rating of all such appliances may be reduced to 75%.

Ranges, cook-tops, and ovens use NEC Table 220.55. For a single household range rated 12 kW or less, the demand is 8 kW. For ranges over 12 kW, adjust per the table notes. For multiple ranges in apartments, the demand per unit drops dramatically. Twelve ranges at 12 kW each have a combined demand of only 27 kW versus 144 kW connected load.

Clothes dryers use NEC 220.54. The demand load is 5,000 watts or the nameplate rating, whichever is larger, for each dryer. For five or more dryers, Table 220.54 provides demand factors starting at 80% for 5 dryers and decreasing to 35% for 40 dryers.

Heating and air conditioning loads are computed at 100% of nameplate but you use only the larger of the two under NEC 220.60, since they do not operate simultaneously in most systems. This non-coincident load provision can significantly reduce the total demand.

Single-Phase vs Three-Phase Transformer Sizing

Single-phase transformers serve residential and small commercial loads. The demand load in VA divided by the secondary voltage gives the current. A 24,000 VA demand at 240V single-phase is 100 amps — a standard 100A residential service.

Three-phase transformers serve commercial and industrial loads. The demand in VA divided by (voltage × 1.732) gives the line current. A 150,000 VA demand at 208V three-phase draws 150,000 ÷ (208 × 1.732) = 416 amps.

Phase balance matters for three-phase sizing. If the load is heavily single-phase (common in apartments and offices with 120V loads), the transformer must be sized for the most heavily loaded phase multiplied by three, not the average of all phases. An unbalanced load of 50 kVA on phase A, 40 kVA on phase B, and 30 kVA on phase C requires a 150 kVA transformer (50 × 3), not 120 kVA.

Formula: Transformer kVA from demand load:
Single-phase: kVA = Total VA demand ÷ 1,000
Three-phase: kVA = Total VA demand ÷ 1,000

Current from kVA:
Single-phase: I = kVA × 1,000 ÷ V
Three-phase: I = kVA × 1,000 ÷ (V × 1.732)

Selecting Standard kVA Sizes and Growth Allowance

Transformers come in standard sizes. Single-phase: 10, 15, 25, 37.5, 50, 75, 100, 167, 250, 333, 500 kVA. Three-phase: 15, 30, 45, 75, 112.5, 150, 225, 300, 500, 750, 1000, 1500, 2000, 2500 kVA. Your calculated demand must be rounded up to the next standard size.

Allow 20% to 25% growth margin above calculated demand for future load additions. A calculated demand of 185 kVA should use a 225 kVA transformer, not a 200 kVA custom unit. The 225 kVA provides 22% growth capacity and is a readily available standard size with better lead time and lower cost than a non-standard unit.

Transformer efficiency peaks at about 50% to 70% of rated load. A transformer running at 30% load has higher percentage losses than one at 60% load because no-load core losses are constant regardless of loading. Extreme oversizing wastes energy 24/7 through elevated no-load losses.

For pad-mount utility transformers, the utility typically owns and sizes the transformer based on your submitted load data. For customer-owned dry-type transformers inside buildings, the electrical engineer specifies the size. In either case, accurate demand calculations are essential.

Tip: Standard three-phase transformer sizes (kVA):
15, 30, 45, 75, 112.5, 150, 225, 300, 500, 750, 1000, 1500, 2000, 2500

Rule of thumb: Select the next standard size above calculated demand + 20% growth factor.

Impedance and Available Fault Current

Transformer impedance, expressed as a percentage (%Z), determines the maximum available fault current on the secondary side. A typical dry-type transformer has 4% to 6% impedance. Lower impedance means higher available fault current, which affects overcurrent protection device ratings.

Available fault current (amps) = Transformer FLA ÷ (%Z / 100). A 225 kVA, 208V three-phase transformer with 5.75% impedance has an FLA of 625A. Available fault current = 625 / 0.0575 = 10,870 amps. All downstream breakers and panels must have an interrupting rating equal to or greater than this value.

NEC 110.9 requires equipment to have adequate interrupting ratings. Standard residential panels are rated 10,000 AIC. Commercial panels are typically 14,000 to 65,000 AIC. If your available fault current exceeds the panel's rating, you need higher-rated equipment or a current-limiting device.

Formula: Available fault current:
I_fault = I_FLA ÷ (% Impedance ÷ 100)

Example: 500 kVA, 480V, 5.75%Z:
FLA = 500,000 ÷ (480 × 1.732) = 601A
I_fault = 601 ÷ 0.0575 = 10,452A

Frequently Asked Questions

Oversizing increases equipment cost and no-load losses. A 500 kVA transformer has roughly twice the core losses of a 300 kVA unit, running 24/7 regardless of loading. Moderate oversizing of 20% to 25% above demand is acceptable for growth. Extreme oversizing wastes energy and money.
Always use demand load calculated per NEC Article 220. Connected load is the total nameplate rating of everything installed. Demand load applies diversity factors that reflect real usage patterns. Connected load dramatically oversizes transformers.
Transformers can handle short-term overloads, typically 150% for two hours, but continuous loading above nameplate accelerates insulation aging and shortens life. IEEE C57.91 provides overload guidelines. Sustained loading above 100% is not recommended for dry-type transformers.
Dry-type transformers use air cooling, are installed indoors, and are typically used up to 2,500 kVA. Oil-filled transformers are more efficient, handle higher loads, and are installed outdoors on pads. Utility transformers are almost always oil-filled.
Disclaimer: Transformer sizing must comply with the current NEC and utility requirements. This guide covers NEC Article 220 general methods. Optional calculation methods under Article 220 Part IV and specific occupancy rules may apply. Consult a licensed electrical engineer for commercial and industrial projects.

Calculators Referenced in This Guide

Electrical Live

Wire Sizing Calculator

Find the right AWG wire gauge for any electrical run. Enter amps, distance, and voltage to get NEC-compliant sizing with derating, voltage drop, and copper vs aluminum cost comparison.

Electrical Live

Panel Load Study

Do you actually need a panel upgrade? Walk your breaker panel with NEC Article 220 demand factors. See connected load vs. calculated demand and test whether an EV charger, heat pump, or hot tub fits.

Electrical Live

Electrical Service & Transformer Sizing Calculator

Size transformers using NEC Article 220 demand factors. Enter your load inventory to calculate demand kVA and select the standard transformer size for single-phase or three-phase service.

Related Guides

Electrical 9 min

NEC Conduit Fill Rules Explained

How NEC Chapter 9 conduit fill calculations work. Tables 1, 4, and 5 explained with examples for EMT, IMC, RMC, and mixed conductor types.