Skip to main content
Productivity 9 min read Feb 25, 2026

Construction Man-Hour Estimating

Unit rates, productivity factors, and the math that turns man-hours into calendar days

Every construction bid, schedule, and labor budget starts with a man-hour estimate. Get it wrong by 15% and you either lose the bid or lose money executing it. Man-hour estimating combines published unit rates (from databases like RS Means, Richardson, or company historical data) with site-specific productivity adjustments to predict how many labor hours a scope of work will require. The estimate then converts to crew sizes, durations, and calendar days to populate the project schedule.

The challenge is not finding unit rates—databases provide those. The challenge is accurately adjusting for the six productivity factors that can swing actual labor by 30–50% from the book rate: weather, site congestion, overtime fatigue, crew experience, supervision quality, and rework. This guide covers the estimating process, the adjustment factors, and the common mistakes that produce estimates disconnected from field reality.

Unit Rates and Crew Productivity

A unit rate expresses labor in hours per unit of installed work: man-hours per linear foot of pipe, per cubic yard of concrete, per each valve installed, per ton of steel erected. Published databases like RS Means provide these rates for hundreds of work items, calibrated to national average conditions with a crew of average skill and experience working a standard 40-hour week. The rates include not just the direct installation time but also material handling, layout, and incidental tasks that are part of a normal workday.

Crew productivity takes the unit rate one step further by defining the crew composition (e.g., 1 foreman + 2 journeymen + 1 apprentice + 1 laborer) and calculating output per crew-day. If a 4-person pipe crew can install 120 linear feet of 4-inch steel pipe per 8-hour day, and the project scope is 6,000 linear feet, the duration is 50 crew-days. The man-hours are 50 days × 4 people × 8 hours = 1,600 man-hours. This crew-based approach is more accurate than multiplying unit rates by total quantities alone because it accounts for crew interactions and the practical limit of how many people can work in a space simultaneously.

Company historical data is always more accurate than published databases because it reflects your specific crews, equipment, practices, and typical conditions. Maintain a feedback loop: track actual man-hours per unit on completed projects, compare to estimates, and build adjustment factors for future bids. Companies that do this consistently achieve estimate accuracy within ±5–8% on familiar work types, compared to ±15–25% when relying solely on published rates.

Tip: Historical tracking: Create a simple spreadsheet for each project: scope quantity, estimated man-hours, actual man-hours, and the ratio. After 3–5 projects, you will have company-specific productivity factors far more accurate than any published database.
Productivity

Job Labor Estimator

Estimate construction man-hours by trade and task with productivity adjustments for weather, overtime, site conditions, night shift, confined space, and elevated work.

Launch Calculator →

The Six Productivity Factors

1. Weather (factor: 0.70–1.00): Extreme heat (>95 °F) reduces productivity by 15–30% due to mandatory rest breaks, PPE burden, and cognitive impairment. Cold weather (<32 °F) adds layered clothing that reduces dexterity, material handling difficulties (frozen ground, ice), and warm-up time. Rain and wind cause direct work stoppages. Budget weather days based on historical climate data for the project location and season—30-year averages from NOAA are a good starting point.

2. Site congestion (factor: 0.70–0.95): Congested sites (turnarounds, plant interiors, urban buildings) reduce productivity through restricted access, material staging constraints, interference between trades, and longer walking distances from laydown to work face. The more trades working in the same area simultaneously, the worse the congestion factor. A greenfield site with good access might warrant 0.95. A packed refinery turnaround with 40 crafts on top of each other might justify 0.70–0.75.

3. Overtime fatigue (factor: 0.85–0.95): Sustained overtime degrades productivity per hour worked. After 4 weeks of 50-hour weeks, productivity per hour drops to about 85% of baseline. At 60-hour weeks for 8+ weeks, it drops to 65–70%. The lost productivity on overtime hours often exceeds the extra output gained. 4. Crew experience (factor: 0.80–1.10): A highly experienced crew on familiar work can exceed book rates (1.05–1.10). A crew performing unfamiliar tasks or with many green hands may produce only 80–90% of book output. 5. Supervision ratio: Inadequate supervision (foreman-to-worker ratios exceeding 1:12 for complex work) directly reduces productivity through rework, idle time, and poor coordination. 6. Rework factor (1.02–1.15): Every project has some rework. Allow 2–5% for well-managed projects and 10–15% for fast-track or design-incomplete work.

Formula: Adjusted man-hours: Base Man-Hours × (1 / Weather Factor) × (1 / Congestion Factor) × (1 / OT Factor) × (1 / Crew Factor) × Rework Factor = Adjusted Man-Hours. Example: 1,000 base × (1/0.85) × (1/0.80) × (1/0.90) × (1/1.0) × 1.05 = 1,715 adjusted man-hours.

Converting Man-Hours to Calendar Days

The conversion from man-hours to calendar days requires three inputs: total adjusted man-hours, crew size, and the work schedule. If the adjusted estimate is 3,200 man-hours, the crew is 8 people, and the schedule is 10 hours/day, 6 days/week: crew-hours per day = 8 × 10 = 80. Working days = 3,200 ÷ 80 = 40 working days. Calendar days (at 6 days/week) = 40 × 7/6 = 46.7, rounded to 47 calendar days. Add weather days, holidays, and mobilization/demobilization time to get the total duration.

The critical mistake is confusing man-hours with crew-hours. A 3,200 man-hour estimate does not mean 3,200 hours of elapsed time—it means 3,200 person-hours of effort. An 8-person crew working 10-hour days consumes 80 man-hours per calendar day. Dividing total man-hours by crew-hours-per-day gives working days, not calendar days. Always account for non-work days (weekends, holidays, planned shutdowns, weather days) when converting to calendar duration.

Also verify that the crew size is feasible for the work area. Putting 20 people in a 500-square-foot mechanical room does not halve the duration compared to 10 people—congestion losses may actually increase total man-hours. There is an optimal crew size for every work scope, beyond which adding people increases cost without reducing duration. Experienced estimators and superintendents know these limits intuitively; newer estimators should discuss crew sizing with field supervision before finalizing schedule durations.

Tip: Rule of thumb: Allow 1.15–1.25 as a calendar-day conversion factor on top of working days to account for weekends (on a 5-day schedule), holidays, and weather. For a 6-day schedule, the factor is 1.08–1.15. For a 7-day schedule (turnarounds), use 1.02–1.05 for holidays only.
Productivity

Rain Day & Weather Delay Tracker

Track weather delay days against contract allowance, project schedule impact, and compare delay costs versus Saturday make-up work with regional precipitation benchmarks.

Launch Calculator →

Common Estimating Mistakes

Optimism bias: Estimators consistently underestimate labor by 10–20% because they envision ideal conditions: full crews, no weather delays, no rework, no material wait time. Counter this by using historical actuals as a reality check and by applying productivity factors before finalizing the estimate, not as an afterthought.

Missing scope: The biggest man-hour busts come not from wrong unit rates but from incomplete quantity takeoffs. Missed items—hangers, supports, small-bore connections, temporary facilities, testing, and punch list work—individually seem minor but collectively add 10–20% to actual labor. Walk the drawings specifically looking for items that generate labor but are easy to overlook. On renovation and demolition work, the hidden conditions factor (asbestos, unforeseen structural conflicts, as-built inaccuracies) can add 15–30% to the estimate.

Ignoring learning curve: The first unit of any repetitive task takes significantly longer than the 50th. The construction learning curve (typically an 80–90% curve, meaning each doubling of cumulative quantity reduces per-unit time by 10–20%) should be factored into estimates for highly repetitive work like curtain wall installation, modular piping, or repetitive floor layouts. Conversely, one-off or unique installations should be estimated at the "first unit" rate, not the average from a database that assumes repetition.

Warning: The 80% rule: If your estimate represents 80% of the scope and you assume the missing 20% is "included," you will overrun. Missing scope is the #1 cause of labor budget overruns, ahead of productivity losses. Force yourself to estimate every line item, even rough-order-of-magnitude for minor items.

Contingency and Escalation

Labor contingency accounts for the known unknowns: productivity losses you cannot predict specifically but know will occur. The appropriate contingency percentage depends on project definition: a detailed estimate from 100% complete drawings might carry 5–8% labor contingency. A conceptual estimate from 30% design might carry 15–25%. Standard industry guidelines (AACE International) define contingency ranges by estimate class, from Class 5 (conceptual, ±30–50%) to Class 1 (definitive, ±3–10%).

Labor rate escalation is separate from contingency and accounts for wage increases over the project duration. Union contracts typically specify annual increases of 2–4%. Open-shop rates follow market conditions. For multi-year projects, apply escalation to the labor cost in each future year at the expected rate. A 3-year project with $10 million in labor and 3% annual escalation costs $10.6 million when properly escalated—a $600,000 difference that can turn a profitable project into a loss if omitted from the bid.

On prevailing wage projects, escalation is especially important because Davis-Bacon wage determinations are updated annually and can increase by $2–5/hr per trade per year in active construction markets. The wage determination locked into your contract at bid may be superseded for option years or contract modifications. Build a prevailing wage escalation assumption into multi-year federal project bids, even if the current WD governs the base period.

AACE estimate classes: Class 5 (conceptual): ±30–50% accuracy. Class 4 (preliminary): ±15–30%. Class 3 (budget): ±10–20%. Class 2 (control): ±5–15%. Class 1 (definitive): ±3–10%. Contingency should match the estimate class, not be a blanket 10% applied to every estimate.
Productivity

Job Labor Estimator

Estimate construction man-hours by trade and task with productivity adjustments for weather, overtime, site conditions, night shift, confined space, and elevated work.

Launch Calculator →

Frequently Asked Questions

RS Means (Gordian) and Richardson Engineering are the most widely used published databases. However, company historical data from completed projects is always more accurate because it reflects your specific crews, equipment, and conditions. Use published rates as a starting point and calibrate with actual project data.
After 4 weeks of sustained 50-hour weeks, apply a 0.85 productivity factor (15% loss per hour). At 60-hour weeks sustained 8+ weeks, apply 0.65–0.70 (30–35% loss). These losses apply to all hours worked, not just overtime hours, because cumulative fatigue affects the entire workweek.
Well-managed projects with complete designs: 2–5% rework factor (multiply man-hours by 1.02–1.05). Fast-track projects with evolving design: 8–12%. Renovation work with unknown conditions: 10–15%. Nuclear and pharmaceutical quality standards: 5–10% due to documentation and inspection requirements.
Divide total adjusted man-hours by (crew size × hours per day) to get working days. Then convert to calendar days by adding non-work days (weekends, holidays, weather days). A 3,200 man-hour scope with an 8-person crew working 10-hour days = 40 working days = roughly 47 calendar days on a 6-day schedule.
It depends on estimate completeness. Conceptual estimates (30% design): 15–25% contingency. Budget estimates (60% design): 10–15%. Definitive estimates (100% design): 5–8%. Follow AACE International guidelines for estimate classification and matching contingency ranges.

Calculators Referenced in This Guide

Productivity & Scheduling Live

Markup vs Margin Calculator

Convert between markup percentage and profit margin. Calculate selling price from cost and desired markup or margin. Includes breakeven analysis and pricing tables.

Productivity & Scheduling Live

Hourly Burden Rate Calculator

Calculate true hourly labor cost including wages, benefits, payroll taxes, insurance, overhead, and utilization rate. Essential for job costing and bid pricing in the trades.

Productivity Live

Job Labor Estimator

Estimate construction man-hours by trade and task with productivity adjustments for weather, overtime, site conditions, night shift, confined space, and elevated work.