Temporary Event Power Distribution Calculator
Generator Sizing, Distro Panel Layout, Circuit Loading, and Cable Gauge for Concerts, Festivals, and Corporate Events per NEC Article 525
Free temporary event power distribution calculator for event electricians, production managers, and technical directors who need to determine total power requirements and distribution layout for concerts, festivals, corporate events, and theatrical productions. Enter your load inventory (sound, lighting, video, catering, HVAC, backline), and the calculator returns the total kW and kVA demand, recommended generator size, distribution panel configuration, and cable sizing for feeder runs from the generator to each distro location.
Temporary event power is governed by NEC Article 525 (Carnivals, Circuses, Fairs, and Similar Events) and Article 590 (Temporary Installations). Unlike permanent electrical work, event power requires rapid setup and teardown, often with generator power, long cable runs over uneven terrain, and loads that vary dramatically between sound check and show time. Undersized generators cause voltage sag, frequency drift, and ground fault issues that crash sensitive audio and video equipment. Oversized generators waste fuel and rental cost. The correct sizing accounts for inrush currents from motor loads (HVAC, refrigeration), power factor of lighting and audio loads, and a diversity factor because not all loads operate simultaneously at full capacity.
The calculator also sizes the feeder cables from the generator to each distribution panel using NEC ampacity tables with derating for ambient temperature and cable bundling. It flags any circuit that exceeds 80% of the conductor ampacity (the NEC continuous load threshold) and recommends the next larger cable size.
Calculate SPL levels for the audio system
Inverse Square Law / SPL Calculator →Calculate projection throw and brightness for video
Projection Throw & Lens Calculator →Check voltage drop on long cable runs from the generator
Voltage Drop Calculator →How It Works
-
Enter Load Inventory
List every load by department: sound system (amplifiers, consoles, processing), lighting (conventional and LED fixtures, dimmers, moving lights), video (projectors, LED walls, cameras, switchers), catering (ovens, warmers, refrigeration), HVAC (portable AC units, heaters), and backline (guitar amps, keyboards). Enter the nameplate wattage or amperage for each.
-
Apply Demand and Diversity Factors
Set the demand factor for each load category. Sound and video typically run at 70-80% of nameplate. Conventional lighting dimmers rarely run at full simultaneously (50-70% diversity). LED lighting is closer to 100%. Catering loads depend on the menu and service timing. The calculator applies these factors to reduce the total from the raw nameplate sum.
-
Select Generator and Distribution
Based on the total kVA demand, the calculator recommends the generator size (or multiple generators for redundancy), the number of distribution panels needed, and the circuit configuration (single-phase 120/208V or three-phase 120/208V or 277/480V for large systems).
-
Review Cable Sizing and Layout
Check the feeder cable size for each run from the generator to each distro panel, the branch circuit loading at each panel, and any circuits that need upsizing. The calculator accounts for cable length, ambient temperature derating, and the 80% continuous load rule.
Built For
- Event electricians sizing generator rentals and distro packages for outdoor concerts and festivals
- Production managers preparing power plots and technical riders for touring shows and corporate events
- Technical directors planning the electrical infrastructure for multi-day festivals with multiple stages
- Venue managers verifying that house power capacity is sufficient for an incoming production's technical rider requirements
Features & Capabilities
Load Inventory by Department
Organizes loads by production department (sound, lighting, video, catering, HVAC, backline, misc) with typical wattage presets for common equipment. Shows the subtotal for each department and the combined total after demand and diversity factors.
Generator Sizing with Power Factor
Sizes the generator in both kW and kVA, accounting for the aggregate power factor of the load mix. Shows the difference between kW (real power) and kVA (apparent power) and explains why the generator kVA rating must exceed the total kVA demand, not just the kW.
Feeder Cable Sizing
Sizes feeder cables (typically 4/0, 2/0, or cam-lock) for each run from generator to distro panel per NEC ampacity tables. Applies ambient temperature derating and flags any run that exceeds 80% of conductor ampacity under the continuous load rule.
Three-Phase Balancing
For three-phase distribution, shows the load on each phase (A, B, C) and flags imbalances greater than 10% between phases. Phase imbalance causes neutral current, voltage asymmetry, and can trigger generator protection relays on sensitive units.
Frequently Asked Questions
Learn More
Sound System SPL & Coverage Design
How to calculate sound pressure level at distance using the inverse square law, amplifier power gain, speaker arrays, and environment factors.
Projector Throw Ratio & Screen Brightness
How to calculate throw ratio, select lenses, and verify screen brightness in foot-lamberts for AV installations and live events.
Temporary Event Power Distribution
How to size generators, feeder cable, and company switches for live events with 3-phase load balancing across audio, lighting, video, and motor loads.
Related Tools
Inverse Square Law / SPL Calculator
Calculate sound pressure level at any distance from speaker sensitivity, amplifier power, array configuration, and environment.
Projection Throw Ratio & Lens Calculator
Calculate projector throw ratio, lens type, and screen brightness in foot-lamberts for AV installations.