Change orders are where contractors lose the most money with the least awareness. The direct cost of extra work is obvious: more material, more labor, more time. But the indirect costs, the ones that eat your profit, are the ones most contractors never price. Extended general conditions, schedule compression on unchanged work, productivity losses from stop-start disruptions, re-sequencing of downstream trades, and the administrative burden of managing scope changes all cost real money.
This guide covers how to identify, document, and price change orders so you recover your full cost. The contract provisions in AIA A201 (2017) and ConsensusDocs 200 serve as the framework, though the principles apply regardless of which contract form you use.
What Your Contract Says About Changes
Every standard construction contract includes a changes clause. Understanding what it says before you sign is critical, because once the contract is executed, the changes clause defines your rights and obligations when scope shifts.
AIA A201-2017, Article 7 defines three types of changes:
- Change Order (Section 7.2): A written agreement signed by owner, contractor, and architect that modifies the contract sum, contract time, or both. This is the gold standard: everyone agrees on the scope, cost, and time impact before the work proceeds.
- Construction Change Directive (Section 7.3): A written order signed by the owner and architect directing a change, even without the contractor's agreement on cost or time. The contractor must proceed with the work while the pricing is negotiated. This is common on fast-track projects where the owner cannot wait for pricing before starting changed work.
- Minor Change (Section 7.4): A written order by the architect for minor changes that do not affect the contract sum or time. These do not require the contractor's agreement, but they also cannot increase your cost.
ConsensusDocs 200, Article 8 uses a simpler framework: the owner issues a Change Order Request, the contractor prices it, and if both parties agree, it becomes a Change Order. If they disagree, the owner can issue a Work Directive (similar to AIA's Construction Change Directive), and the contractor must proceed while preserving the right to dispute the cost.
The critical takeaway: under both contract forms, you are required to proceed with changed work even if you disagree with the pricing. Your remedy is to document your costs contemporaneously and resolve the dispute later. Refusing to perform directed changes is a breach of contract.
Change Order Cost Calculator
Calculate the true cost of a change order including direct costs, extended overhead, remobilization, rework, engineering, and bond adjustments. Shows what contractors leave on the table when they only price direct costs.
Extended Overhead: The Most Underpriced Item
When a change order extends the project schedule, your general conditions costs keep running. The superintendent is still on site. The trailer, temporary power, portable toilets, and dumpsters are still being rented. Your project manager is still managing. Insurance premiums continue. These costs are real, quantifiable, and almost always underpriced or omitted entirely from change order proposals.
Calculating extended general conditions:
Daily General Conditions Rate = Total Project General Conditions / Original Contract Duration (working days)
If your general conditions budget is $180,000 for a 240-working-day project, your daily rate is $750/day. A change order that extends the schedule by 15 working days costs $11,250 in extended general conditions alone, before you price a single hour of labor or dollar of material for the changed work itself.
Home office overhead (Eichleay formula): In addition to field general conditions, change-order delays can entitle you to recovery of home office overhead. The Eichleay formula, recognized by federal boards of contract appeals and many state courts, calculates the daily home office overhead rate allocable to the delayed project:
Step 1: Allocable OH = (Contract Billings / Total Billings During Period) × Total Home Office OH Step 2: Daily Rate = Allocable OH / Original Contract Days Step 3: Extended OH = Daily Rate × Delay Days
The Eichleay formula applies most clearly to government contracts and to delays that are "suspensions" of work (your crew is on standby, unable to take other work). On private work, your entitlement to home office overhead depends on the contract language and the jurisdiction.
Change Order Cost Calculator
Calculate the true cost of a change order including direct costs, extended overhead, remobilization, rework, engineering, and bond adjustments. Shows what contractors leave on the table when they only price direct costs.
Schedule Impact Documentation
Every change order that affects the critical path entitles you to a time extension. The challenge is proving that the change actually impacted the critical path, not just that you did extra work.
Contemporaneous schedule updates are your best evidence. Update your CPM schedule monthly at minimum. When a change order is issued, insert the changed work activities into the schedule and run the forward pass. If the project completion date shifts, you have a documented critical path impact.
Types of delay:
- Critical delay: Extends the project completion date. Entitles you to a time extension and potentially extended overhead recovery.
- Non-critical delay: Consumes float on a non-critical path. Does not extend completion, but may reduce your scheduling flexibility for future work.
- Concurrent delay: Both the owner-caused change and a contractor-caused delay affect the critical path simultaneously. Most jurisdictions apportion responsibility, but the rules vary. Document everything and let the schedule analysis sort it out.
What to document for each change:
- Date the change was directed or discovered
- Activities affected (by schedule activity ID)
- Duration of added or modified activities
- Logic ties to predecessor and successor activities
- Resource impacts (crew size, equipment)
- Updated schedule showing the time impact
If you do not maintain an updated CPM schedule, proving critical path impact becomes an opinion fight between your expert and the owner's expert. That is expensive and unpredictable. A contemporaneous schedule is a fact.
Change Order Cost Calculator
Calculate the true cost of a change order including direct costs, extended overhead, remobilization, rework, engineering, and bond adjustments. Shows what contractors leave on the table when they only price direct costs.
How to Document Change Orders for Maximum Recovery
The quality of your documentation determines the quality of your recovery. Poorly documented change orders get negotiated down. Well-documented change orders get paid.
At the time of the change:
- Photograph existing conditions before any changed work begins
- Log the date, time, and person who directed the change
- Issue written notice within the contract-required timeframe (typically 7-21 days under AIA and ConsensusDocs)
- If the change was verbal, follow up with a written confirmation ("Per our conversation on [date], you directed us to...")
During the changed work:
- Track labor hours daily on a separate cost code for each change order
- Keep material invoices and delivery tickets segregated
- Photograph the work in progress at key milestones
- Document equipment usage (type, hours, dates)
- Record any impacts to other ongoing work
In the change order proposal:
- Reference the specific contract section authorizing the change (e.g., "Per AIA A201 Section 7.3.3")
- Include detailed labor breakdowns by trade and task
- Attach material quotes or invoices
- Show equipment rates from published rate guides (Blue Book, FEMA Schedule) or your internal rate schedule
- Itemize overhead and profit as separate line items
- Include the schedule impact analysis
- Attach photographs
The proposal should tell a complete story: what changed, why it changed, what it cost, and how long it took. A reviewer should be able to approve it without needing to call you for additional information.
Change Order Cost Calculator
Calculate the true cost of a change order including direct costs, extended overhead, remobilization, rework, engineering, and bond adjustments. Shows what contractors leave on the table when they only price direct costs.
Markup and Profit on Change Order Work
Most contracts specify the allowable markup on change order work. Common contractual markups:
| Contract Type | Typical O&P on Self-Performed Work | Typical Markup on Sub Work |
|---|---|---|
| AIA A201 (negotiated) | 15-20% | 5-10% |
| Federal (FAR) | 10% overhead + 10% profit | 10% overhead + 10% profit |
| State DOT | 15% + 5% (varies by state) | 5-10% |
| ConsensusDocs | 15% (default, negotiable) | 5% (default, negotiable) |
If your contract does not specify a markup, AIA A201 Section 7.3.3.3 allows "reasonable" overhead and profit. What is reasonable depends on the scope and complexity of the change. A straightforward material substitution warrants less markup than a complex re-sequencing of work in an occupied building.
On subcontractor change orders, you are entitled to markup on top of the subcontractor's price. This is your compensation for managing, coordinating, and taking responsibility for the sub's changed work. The sub applies their own markup (typically 15-20%), and you add your prime contractor markup (typically 5-10%) on top of the sub's total.
Watch for contract language that limits the "tier" of markups. Some federal and state contracts prohibit sub-sub markups or limit the total number of markup tiers to prevent cost inflation on multi-tier subcontracted work.
Change Order Cost Calculator
Calculate the true cost of a change order including direct costs, extended overhead, remobilization, rework, engineering, and bond adjustments. Shows what contractors leave on the table when they only price direct costs.
Change Order Cost Calculator
Calculate the true cost of a change order including direct costs, extended overhead, remobilization, rework, engineering, and bond adjustments. Shows what contractors leave on the table when they only price direct costs.