Change Order Cost Calculator
Calculate the fully-loaded cost of a change order including labor, materials, overhead, profit, and schedule impact
Free change order cost calculator for contractors, project managers, and owners who need to price scope changes accurately. Enter the direct costs of the changed work (labor hours, material quantities, equipment), then apply contract-specified markup rates for overhead and profit. The calculator adds often-overlooked costs: extended general conditions, schedule compression, rework of completed work, and bond premium increases. Returns the total change order price with a line-item breakdown suitable for AIA G701 or ConsensusDocs change order forms.
Build the original bid to compare against the change
Job Bid Builder →Calculate burdened labor rates for change order pricing
Hourly Burden Calculator →Estimate equipment costs included in the change
Equipment Ownership Cost Calculator →How It Works
-
Enter Direct Costs of Changed Work
Input the labor hours and burdened hourly rates for each trade involved in the change. Add material costs from supplier quotes or catalog pricing. Include equipment rental or ownership costs for any additional equipment needed. If subcontractors are involved, enter their quoted price for the changed scope.
-
Apply Contract Markup Rates
Enter the overhead and profit percentages specified in your contract. AIA A201 does not set fixed percentages but requires them to be agreed upon. Common ranges are 10% to 15% overhead and 5% to 10% profit on self-performed work, and 5% to 10% combined markup on subcontractor work. Check your contract's General Conditions or Supplementary Conditions for the exact rates.
-
Add Schedule Impact Costs
If the change extends the project duration, enter the number of additional days and your daily general conditions cost (superintendent salary, site facilities, insurance, permits). The calculator multiplies the daily rate by the delay duration. For acceleration costs (overtime to maintain the original schedule), enter the overtime premium rates separately.
-
Include Rework and Demolition
If the change requires removing or modifying completed work, enter the demolition labor, disposal costs, and replacement material costs. This is frequently overlooked on change orders where the design change affects already-installed elements. Document the completed work with photos before demolition.
-
Review Total Change Order Price
The output shows a line-item breakdown of direct costs, overhead, profit, schedule impact, rework, and bond premium adjustment. The total change order price is suitable for submission on standard forms. Export as PDF for your change order documentation package.
Built For
- General contractors pricing owner-requested scope changes on commercial construction projects
- Subcontractors preparing change order proposals in response to revised drawings or field conditions
- Project managers evaluating contractor-submitted change orders for reasonableness before approval
- Owners and their representatives estimating the cost impact of design changes before issuing an architect's supplemental instruction
- Construction attorneys reviewing change order pricing for dispute resolution or claims analysis
- Government contracting officers evaluating equitable adjustment requests under FAR Part 43
Features & Capabilities
Hidden Cost Identification
Prompts you to consider costs that are commonly missed on change orders: extended general conditions, bond premium increases, permit revision fees, re-inspection costs, material restocking fees, and productivity loss from disrupted sequencing. Each hidden cost category has an input field with typical ranges to guide your estimate.
Contract Markup Compliance
Applies overhead and profit at the rates specified in your contract, with separate rates for self-performed work and subcontractor pass-through. Flags when your calculated markup exceeds typical contract limits so you can verify before submission.
Assumptions
- Labor rates are assumed to be fully burdened including payroll taxes, workers' compensation, and benefits.
- Overhead and profit percentages are applied per the contract terms. The calculator does not enforce any specific percentage; you must enter the rates from your agreement.
- Schedule impact costs use a daily general conditions rate that you provide. This should include all time-dependent costs: site supervision, facilities, utilities, insurance, and financing.
- Bond premium adjustment assumes the surety charges on the revised contract amount. Not all bond modifications trigger additional premium; check with your bonding agent.
- Productivity loss factors are estimates. Actual productivity impact depends on timing, trade stacking, and site conditions.
Limitations
- Does not calculate delay damages (liquidated or actual) that may be assessed by the owner if the change causes a schedule overrun.
- Does not model cumulative impact of multiple change orders on overall project productivity (the "ripple effect" or "cumulative impact" claim).
- Does not generate formal change order documents (AIA G701, ConsensusDocs). Use the output as pricing backup for those forms.
- Does not assess whether the change is within the general scope of the contract, which determines whether it is a valid change order or a cardinal change.
References
- AIA A201-2017 General Conditions of the Contract for Construction, Article 7 (Changes in the Work). Defines change order procedures, cost determination methods, and contractor entitlements.
- ConsensusDocs 200 Standard Agreement and General Conditions, Section 8 (Changes). Alternative contract form with similar change order provisions.
- FAR Part 43 - Contract Modifications (Federal Acquisition Regulation). Governs equitable adjustments on federal construction contracts.
- AACE International Recommended Practice 25R-03 - Estimating Lost Labor Productivity in Construction Claims.
Frequently Asked Questions
Learn More
Change Order Pricing: The Hidden Costs Contractors Miss
Extended overhead, remobilization, rework, ripple effects, and engineering costs that most contractors forget to include in change order pricing. AIA A201 and FAR provisions explained.
Related Tools
Local SEO Foundry
Plan and track your local SEO strategy. Manage business citations, review profiles, NAP consistency, and Google Business Profile optimization for contractors and local service businesses.
DIY Project Plan Builder
Step-by-step build plans for mini-split installs, generator setups, shop heaters, outbuilding wiring, and water heater replacements. Get sized tool and material lists based on your calculator results.
Shift Schedule Generator
Generate DuPont, Pitman, 4-on-4-off, and Continental shift calendars with built-in pay and overtime calculator. See your gross earnings per pay period, customize crew colors, download printable PDF schedules, and export ICS calendar files.